Pursuant to the new regulations, some ISF elements must be submitted no later than 24 hours before the cargo is laden aboard the vessel at the foreign port. When cargo is first laden aboard a feeder vessel, are these elements required no later than 24 hours before the cargo is laden aboard the feeder vessel or the vessel destined to the United States? When are ISFs for FROB required?
Click Here For More Information
For ISF elements that must be submitted no later than 24 hours before the cargo is laden aboard the vessel at the foreign port, the elements must be submitted no later than 24 hours before the cargo is laden aboard a vessel destined to the United States. Similarly, for FROB, the required elements must be submitted prior to lading aboard a vessel destined to the United States.